Concrete Calculator

Calculate concrete volume and the cement, sand and aggregate needed for a slab using an M20 mix.

Formula last reviewed 4 August 2026 · How we verify our calculators

Enter details

m
m
m

Concrete volume

0.90 m³

Cement
8 bags
Sand
0.38 m³
Aggregate
0.76 m³

Updates live as you type

Frequently asked questions

Multiply length × width × thickness, all in metres. A 3 × 2 m slab that is 0.15 m thick is 0.9 cubic metres of concrete.

M20 is a common structural grade with a 1:1.5:3 ratio of cement, sand and aggregate, used for slabs, beams and columns in residential work.

Dry materials have voids that fill when mixed with water, so the dry quantity is about 1.54 times the finished wet volume. This factor is built into the estimate.

Roughly 8 bags (about 400 kg) of cement per cubic metre of M20 concrete, varying slightly with the exact mix and assumptions.

Point nine cubic metres, and the bags that go into it

A slab 3 m × 2 m × 0.15 m thick is 0.90 m³ of concrete. At M20 grade that needs about 8 bags of cement, 0.38 m³ of sand and 0.76 m³ of coarse aggregate.

Volume = length × width × thickness, with every dimension in metres. The commonest error is mixing units — entering thickness in millimetres or inches while length is in metres inflates the answer by orders of magnitude. 150 mm is 0.15 m.

How the materials are derived

Concrete is specified by grade, which describes the ratio of cement to sand to aggregate and the compressive strength it achieves at 28 days:

  • M15 — 1 : 2 : 4 — plain concrete, levelling courses, non-structural fill
  • M20 — 1 : 1.5 : 3 — general RCC, residential slabs, columns and beams
  • M25 and above — designed mixes rather than nominal ratios, used for structural work to specification

For M20, the dry volume needed is roughly 1.54 times the wet volume, because the dry ingredients lose bulk as they compact and the voids fill with water. So 0.90 m³ of finished concrete requires about 1.39 m³ of dry material, divided in the 1 : 1.5 : 3 proportion.

Cement is then converted from volume to bags, since it is sold that way: a standard bag is 50 kg, with a bulk density of about 1,440 kg/m³, so one bag is roughly 0.0347 m³.

Where the estimate meets the site

The figures here are a nominal mix estimate. Real work departs from it in several ways worth planning for:

Wastage. Spillage, over-ordering at the corners of a pour and material left in the mixer typically add 5–10%. Order accordingly rather than exactly.

Water-cement ratio. Strength depends heavily on it — roughly 0.45 to 0.55 by weight for M20. Adding water to make concrete easier to place is the single most common way site concrete ends up weaker than specified, and it is invisible until testing.

Aggregate size and grading. Nominal mixes assume well-graded 20 mm aggregate. Poorly graded material needs more cement for the same strength.

Ready-mix versus site-mix. Above roughly 3–5 m³, ready-mix concrete is usually cheaper, more consistent and faster than mixing on site, and it comes with a delivery note stating the grade.

Curing, which decides the outcome

Concrete does not dry — it hydrates, a chemical reaction that continues for weeks and requires water throughout. Keeping a slab continuously moist for at least 7 days, and ideally 14, is what allows it to reach its design strength.

Concrete cured for three days and then left typically achieves substantially less than its grade strength, and no amount of correct mix proportioning recovers it. In Indian summer conditions, curing is the most frequently skipped and most consequential step on a small site.

Reading the result

The volume is exact arithmetic. The material quantities are estimates from nominal ratios, appropriate for ordering and budgeting on residential work.

For anything structural — a load-bearing slab, a column, a beam carrying a floor above — the mix should come from a design by a qualified engineer, based on the actual loads, exposure conditions and locally available materials, with cube testing to verify. Nominal mixes are a reasonable guide and not a substitute for design.

Common mistakes

Mixing units. Thickness in millimetres against length in metres is the classic error.

Ordering exactly the calculated quantity. Add 5–10% for wastage.

Adding water for workability. It reduces strength directly; use a plasticiser instead if the mix is stiff.

Skipping curing. Seven days minimum, kept genuinely wet.

Using nominal mixes for structural work. Above M20, concrete should be designed rather than proportioned by rule of thumb.